Despite delays, $80M Stateline events center construction mostly on track

The Tahoe South Events Center is expected to be open by early January 2023, slightly pushed back from its original date of late December 2022.

The Tahoe South Events Center is expected to be open by early January 2023, slightly pushed back from its original date of late December 2022. Photo: Bill Rozak / Tahoe Daily Tribune


Despite summer smoke from the Tamarack and Caldor fires, evacuations and fall weather delays pushing back construction, work on the Tahoe South Events Center in Stateline has mostly stayed on track.

Crews lost an estimated 17 days due to fire and five due to a snowstorm in October, but Rick Kozuback, president and CEO of International Coliseums Company — which is overseeing construction of the project — said they are close to making up those days.

The original timeline set Oct. 15 as the day steel erection would be complete, including stairs, beams and trusses. Crews started steel erection on Monday, Nov. 15, and because the weather has been favorable, they are quickly making up for lost time.

Kozuback said that while it would be much better to not have to erect steel in the snow, if the weather turns soon, crews are capable and willing to do so.

In addition, they’ve started winterizing the site so construction can continue through the winter. They’ve laid down mulch and silt fences to keep water from flooding the area.

They’ve also poured asphalt in all the working areas so that they can use heavy equipment without damaging the ground. Kozuback said for people driving by the site, the asphalt may look like a giant parking lot but it will in fact be the future site of the arena.




RELATED: With fire fears in past, South Tahoe casinos focus on future



Kozuback added that some of the subcontractors have experienced staffing shortages but it hasn’t caused any further delays.


Located on the Nevada side of Lake Tahoe's south shore, the $80 million event center is a 143,000-square-foot, multi-use facility that will host concerts, conferences, sporting events and more.


Ground broke in July 2020; the project's economic impact is estimated to be $40-60 million per year, according to the Tahoe Douglas Visitors Authority.


The delays have shifted the opening date slightly, from late December 2022 to early January 2023, but the project remains on budget.

Said Kouzback, “It’s been interesting and challenging but fun and exciting to see this come to fruition.”

Laney Griffo is a reporter for the Tahoe Daily Tribune. This
 story first published Nov. 19 and is republished here with permission.

Comments

Use the comment form below to begin a discussion about this content.

Sign in to comment